Commercial & Building Moisture Control

Desiccant Dehumidifiers in Water-Damage Restoration: When Refrigerant Equipment Stops Working

When refrigerant equipment stops working: cold buildings, stalled jobs and Class 4 losses. Containment, heat, and measuring materials rather than air.

Written byYakeclimate Engineering TeamEngineering Team
Water-damaged interior prepared for desiccant drying.

A drying job that has stalled with plenty of air movers running is almost never short of airflow. It is either short of heat, short of containment, or asking refrigerant equipment to work at a temperature and humidity where it cannot.

Desiccant drying equipment operating in a water-damaged building.

Knowing which of those three applies — and recognising the fourth case, where water is bound inside a low-porosity material and no amount of surface air movement will reach it — is what separates a job that finishes on schedule from one that runs for weeks.

Start With the Water Event

The IICRC S500 standard classifies water damage along two axes, and both bear on equipment selection.

Category describes contamination: Category 1 originates from a clean water source, Category 2 carries some contamination, Category 3 is contaminated. Category governs health and safety precautions, what materials can be dried in place versus removed, and containment requirements.

Class describes the drying burden: Class 1 involves the least absorption and evaporation demand; Class 2 affects significant absorption into lower wall cavities; Class 3 carries the greatest evaporation demand with saturation from overhead; Class 4 involves deep penetration into low-porosity materials such as hardwood, concrete and plaster, and calls for specialty drying methods.

Class 4 is the case that most often defeats standard equipment, and the reason is physical rather than a matter of capacity. Water held within a dense material has to diffuse out through the pore structure before it can evaporate — the falling-rate phase described in evaporation, drying rate and dehumidification load. The rate is controlled by the material, and the only external lever that still works is lowering the vapour pressure of the surrounding air, which increases the gradient driving diffusion outward.

That is precisely what desiccant equipment does better than refrigerant equipment.

Where Refrigerant Equipment Runs Out

Refrigerant dehumidifiers, including low-grain refrigerant machines, remove water by condensing it on a cold coil. Two limits govern them.

Capacity falls as air becomes cooler and drier. As the entering air's dew point approaches the coil temperature, the driving force for condensation shrinks. A machine performing well at 30 °C and 80 % RH performs very differently at 12 °C and 45 % RH.

Coil frosting. Below roughly 15–18 °C entering-air temperature the coil surface can drop below freezing, and time is lost to defrost cycles that remove no water.

Both limits bite in exactly the situations restoration work presents: an unheated building in winter, a job that has progressed to the point where the air is already fairly dry, and any attempt to reach the low humidity that Class 4 drying requires.

Desiccant equipment adsorbs water onto a solid medium instead of condensing it, so it is far less temperature-sensitive and can reach much lower humidities. Equipment in this catalogue's desiccant range is specified for −10 to +55 °C, against 5–38 °C for the refrigerant range.

The practical decision rule:

SituationRoute
Warm building, high initial moisture, Class 1–2Refrigerant is efficient and usually sufficient
Unheated building, winter, low temperaturesDesiccant
Job has stalled at a humidity plateauDesiccant — the plateau is the equilibrium moisture content for the current air
Class 4, bound water in dense materialsDesiccant, with heat
Very large open volume, warmRefrigerant, often in numbers
Documentation requires reaching a specific low moisture contentDesiccant

Many jobs use both: refrigerant equipment for the high-load constant-rate phase, desiccant for the falling-rate phase where the last portion of water has to be extracted.

Containment Does More Than Capacity

The single highest-return decision on a drying job, and it is usually free.

A dehumidifier reduces the moisture content of the air it treats. If that air is continuously replaced from the rest of the building, the machine is drying the building rather than the affected area — and the building is much larger than the machine.

  • Close the boundary. Doors shut, openings sheeted, service penetrations and ceiling voids considered.
  • Isolate from the building's HVAC, which will otherwise supply outdoor or adjacent air into the zone and cancel the effect.
  • Route the desiccant reactivation exhaust outside the zone. This stream leaves hot and very humid; discharging it inside the containment returns the water just removed. This is a specific and common error with desiccant equipment.
  • Consider pressure. Slight negative pressure in the zone prevents moist air and odours migrating into occupied areas — often required in Category 2 and 3 work for contamination control reasons as much as drying ones.

The same reasoning, applied to portable equipment generally, is in commercial portable dehumidifiers.

Air Movement and Heat Are Not Optional Extras

The three tools work on different parts of the problem, and each has a phase where it dominates.

Air movement thins the saturated boundary layer at wet surfaces, which accelerates evaporation. It is most effective in the constant-rate phase, while surfaces are still wet. Its returns diminish sharply once the material enters the falling-rate phase — which is why adding fans to a stalled job achieves little.

Heat raises the material's surface temperature, which raises the saturation vapour pressure at that surface and therefore the driving force for evaporation. Saturation vapour pressure roughly doubles for every 10 K in the ambient range, so heat is a powerful lever — and it works on the material, which air movement in the falling-rate phase does not.

Two points about heat that are often missed: it must reach the material, not just the air, so a heated room with a cold slab has not achieved much; and desiccant equipment delivers warm process air as an inherent by-product of adsorption, which is part of why it suits cold-weather work.

Dehumidification maintains the vapour pressure difference and lowers the equilibrium moisture content the material is heading toward. It is the only one of the three that still helps in the final phase.

A stalled job should therefore be diagnosed by asking which phase it is in, not by adding more of whatever is already there.

Measure the Material, Not the Air

Air reaching target does not mean the job is done. Materials dry from the surface inward, so a surface can be dry while the interior is saturated — and the interior is what fails later.

Use appropriate instruments for the material. Pin and pinless moisture meters, and in-situ probes for slabs, answer different questions and have different limitations.

Establish a dry standard. Measure an unaffected area of the same material in the same building to determine what "dry" means for that material in that environment. An absolute reading without this reference is difficult to interpret.

Measure the same locations each time. Mark them. Readings from varying positions produce a trend that reflects position rather than progress.

Record the drying curve. Plotting moisture content over time shows the phase transition — a straight-line fall while surfaces are wet, then a flattening curve — and shows when the job has plateaued rather than progressed.

For concrete slabs, in-situ relative humidity probes to ASTM F2170 measure the condition within the slab, while anhydrous calcium chloride testing to ASTM F1869 reflects surface emission over a 60–72 hour period. They answer different questions and are not interchangeable — a distinction developed in choosing a moisture barrier for concrete floors.

Log the air conditions alongside, inside and outside the containment. A material reading without the corresponding air condition cannot be interpreted.

Documentation

Restoration work is usually reimbursed, and reimbursement depends on records.

What a defensible record contains:

  • Initial assessment: category, class, affected materials and extent, with photographs.
  • The dry standard established for each material type.
  • Daily readings: material moisture at marked locations, air temperature and relative humidity inside and outside containment, and outdoor conditions.
  • Equipment deployed, where, and for how long.
  • Condensate volume where measurable — a direct record of water actually removed.
  • The completion criterion and the readings demonstrating it was met.
  • Any change in scope, with the reason.

A record that shows a drying curve reaching and holding the dry standard is substantially more defensible than one showing dates and equipment counts.

Knowing When to Stop

Two failure modes, in opposite directions.

Stopping early because surfaces feel dry and air readings look acceptable, while material moisture is still elevated. The consequence appears weeks later as odour, mould growth or material failure, and the return visit is at the contractor's cost.

Continuing past the point of return because readings are not improving. A plateau usually means the material has reached its equilibrium moisture content for the current air conditions. Continuing with the same equipment achieves nothing; the options are drier air, more heat, or accepting that the material must be removed.

The distinction is visible in the drying curve, which is another reason to plot it rather than simply record readings.

Information to Prepare

  • The water event: source, category, date, and extent.
  • Affected materials, their construction and thickness, and the class of the loss.
  • Building condition: heated or unheated, sealed or open, and the outdoor conditions.
  • Whether the affected area can be contained, and the containment achievable.
  • Current material moisture readings and the dry standard established.
  • Current air conditions inside and outside the affected area.
  • Equipment already deployed and what has been achieved so far.
  • Available power supply and circuit capacity.
  • Available exhaust route for desiccant reactivation air.
  • The completion criterion, the test method, and any deadline.
  • Occupancy and access constraints.

Discussing a Project

Yakeclimate designs and manufactures industrial dehumidification equipment for complex climate applications, with a focus on agriculture and energy projects.

We co-develop application-specific dehumidification equipment around the operating conditions, interfaces, and integration requirements of the wider project or system.

Restoration methodology, contamination assessment and completion criteria are determined by the restoration professional in accordance with the applicable standard of care and the requirements of the insurer and any authority involved.

Review desiccant rotor dehumidifiers, explore industrial dehumidifiers, or contact Yakeclimate to review the operating conditions for your project.

FAQ

Frequently Asked Questions

When should a desiccant dehumidifier be used instead of a refrigerant one?

When the building is cold, when the job has reached a humidity plateau, or when water is held deep within low-porosity materials — the Class 4 case in IICRC S500, covering hardwood, concrete and plaster. Refrigerant equipment loses capacity as air becomes cooler and drier, and below roughly 15–18 °C entering-air temperature the coil can frost, costing further time to defrost cycles. Desiccant equipment adsorbs water onto a solid medium instead, so it is far less temperature-sensitive and reaches lower humidities.

Why has my drying job stalled despite plenty of air movers?

Because the material has moved from the constant-rate phase into the falling-rate phase, where the limitation is water diffusing out through the material rather than evaporating from a wet surface. Air movement helps a great deal in the first phase and very little in the second. What still helps is lowering the air's humidity — which reduces the equilibrium moisture content the material is heading toward — and adding heat, which raises the material's surface vapour pressure. If readings have flattened entirely, the material has probably reached equilibrium with the current air conditions.

Where should desiccant reactivation air be exhausted?

Outside the containment, always. Reactivation air leaves the machine hot and very humid, and discharging it inside the drying zone returns the water that was just removed. This is a common and costly error. The exhaust route needs to be established when the equipment is positioned, not improvised afterwards.

Does containment really matter more than machine size?

Usually, yes. A dehumidifier reduces the moisture content of the air it treats, and if that air is continuously replaced from the rest of the building, the machine is drying the building rather than the affected area. Closing the boundary, isolating the zone from the building's HVAC, and routing any reactivation exhaust outside the zone typically produce a larger improvement than additional capacity, at no equipment cost.

How do I know when the drying is finished?

By material readings against an established dry standard, not by air readings or by how surfaces feel. Measure an unaffected area of the same material in the same building to determine what dry means there, take readings at marked locations so the trend reflects progress rather than position, and plot the curve. A record showing the curve reaching and holding the dry standard is also what makes the job defensible for reimbursement.

Should heat be added to a drying job?

Often, and it is under-used. Raising the material's surface temperature raises its saturation vapour pressure and therefore the driving force for evaporation — saturation vapour pressure roughly doubles for every 10 K in the ambient range. The important qualification is that the heat has to reach the material rather than just the air: a warm room with a cold slab has not achieved much. Desiccant equipment delivers warm process air inherently, which is part of why it suits cold-weather work.

References

About the author

Yakeclimate Engineering Team

Engineering Team

Yakeclimate technical articles are prepared by the engineering team using inputs from product development, application review, manufacturing, testing, and project support.

View author profile

Continue reading

More on commercial & building moisture control

Project support

Ready to turn the operating conditions into a project brief?

Use the project-input checklist to help our team review the environment, moisture load, interfaces, installation limits, and validation needs from one consistent brief.
Send project requirements